We recently completed a full demolition project at the former Tile Warehouse and Greggs site on Kingsbury Road, Erdington, Birmingham. Appointed by Edmond Shipway, this project formed part of a redevelopment scheme to construct two new retail units – one of which included a drive-through facility.
1016 Kingsbury Road, Erdington, Birmingham, B24 9PZ
Explore more of our work as demolition contractors in Birmingham →
Our demolition team was tasked with the safe and efficient clearance of the site. This included:
Milestone
Date
Start on site
16/01/2023
Temporary off-site
03/02/2023
Returned to site
16/02/2023
Project completion
28/02/2023
Despite the phased programme, the project was completed on time and to the highest safety standards.
This project is just one example of how Jim Wise Demolition delivers reliable, fully managed demolition services in Birmingham and the wider West Midlands. Whether it’s asbestos removal, internal strip-outs, or full structural clearance, we approach every job with precision, planning, and professionalism.
Looking for a trusted demolition contractor in Birmingham?
Click here to learn more about our Birmingham services →
Let me know if you’d like a matching blog post, image captions, or schema markup to support this page further.
If you would like to arrange an appointment with us to discuss a potential project, or if you have a question about what we do, please get in touch with us today and we’ll be more than happy to help you.